Slab tolerances, set-out, access, storage and bracing: a practical checklist so your steel wall frames go up smoothly from the moment they land.
Prefabricated steel wall frames go up quickly, but only if the site is ready for them. Most delays on install day have nothing to do with the frames themselves: they come from the slab, the access or the paperwork. Run through this checklist before the truck is booked.
Check the delivery against the schedule before the truck leaves. Stand panels in the planned order, install temporary bracing as you go, and don't remove it until the permanent bracing and connections are complete. Avoid cutting members to make things fit; if something doesn't line up, stop and call the supplier.
Book any required frame inspection, and keep the engineering documentation together for the certifier. Brief following trades on which members must not be cut or altered.
CADROLL frames come with clear drawings and labelled, sequenced panels, and our team is a phone call away on install day. Talk to us about your next delivery.
Written by
Sudhir Patel
CADROLL
Technical GuidesModular homes are lifted, trucked and craned before anyone lives in them. Here's why light, straight, stable steel frames suit that journey.
Read article→
Technical GuidesThey're both steel, but they're made, sized and used very differently. How to tell which parts of your building need which, and why many projects use both.
Read article→
Technical GuidesTwo steel frame quotes can look similar and end up thousands apart. What to check in inclusions, engineering, variations and support before you sign.
Read article→
Send us your plans for a free drawing review and an itemised steel frame quote.