Before the Truck Arrives: A Site Checklist for Steel Wall Frames

Slab tolerances, set-out, access, storage and bracing: a practical checklist so your steel wall frames go up smoothly from the moment they land.

2 min read

Prefabricated steel wall frames go up quickly, but only if the site is ready for them. Most delays on install day have nothing to do with the frames themselves: they come from the slab, the access or the paperwork. Run through this checklist before the truck is booked.

The slab

  • Check the slab is level and within the tolerances on the framing drawings. High spots and dips mean packing and grinding.
  • Confirm set-out matches the architectural plans: wall positions, openings and overall dimensions.
  • Make sure plumbing and electrical penetrations through the slab are where the frame expects them.
  • Know where hold-down and tie-down fixings go, and that the slab edges allow the required edge distances.

Access and storage

  • Is there room for the delivery truck to get in, turn and unload safely?
  • Have you planned a flat, clear storage area close to where frames will be stood?
  • If a crane or forklift is needed, is it booked and is the ground suitable?

Paperwork and people

  • Do you have the layout drawings, panel schedule, bracing plan and tie-down details on site?
  • Does your crew know how panels are labelled and in what order they'll be installed?
  • Do you have the name and number of someone at your framing supplier who knows the job?

On the day

Check the delivery against the schedule before the truck leaves. Stand panels in the planned order, install temporary bracing as you go, and don't remove it until the permanent bracing and connections are complete. Avoid cutting members to make things fit; if something doesn't line up, stop and call the supplier.

After the frame is up

Book any required frame inspection, and keep the engineering documentation together for the certifier. Brief following trades on which members must not be cut or altered.

CADROLL frames come with clear drawings and labelled, sequenced panels, and our team is a phone call away on install day. Talk to us about your next delivery.

Sudhir Patel

Written by

Sudhir Patel

CADROLL

Keep reading

CADROLL steel frame

Have a Project in Mind?

Send us your plans for a free drawing review and an itemised steel frame quote.